Sanitation Standard Operating Procedures (SSOP)
Document Control
| Field |
Value |
| Document ID |
FS-SSOP-001 |
| Version |
3.2 |
| Effective Date |
2026-01-15 |
| Owner |
Sanitation Manager |
| Approver |
Food Safety Team Leader |
| Review Frequency |
Annual |
1. Pre-Operational Sanitation
1.1 Scope
Pre-operational sanitation covers all cleaning activities performed before the start of production each day, following any shutdown period exceeding 4 hours.
1.2 General Pre-Op Procedure
| Step |
Activity |
Detail |
| 1 |
Dry Clean |
Remove loose debris, dust, and product residues using brushes, scrapers, or vacuum systems. No compressed air for dry cleaning unless HEPA-filtered. |
| 2 |
Pre-Rinse |
Rinse all product contact surfaces with potable water at 38–49 °C (100–120 °F) to remove residual soils. |
| 3 |
Detergent Application |
Apply approved detergent per Master Sanitation Schedule. Ensure foam contact time ≥ 10 minutes. Do not allow foam to dry on surfaces. |
| 4 |
Manual Scrubbing |
Scrub all product contact surfaces with dedicated colour-coded brushes (white = food contact, blue = equipment, red = drains/floor). |
| 5 |
Post-Rinse |
Rinse thoroughly with potable water until all chemical residues are removed. Verify with pH test strips if required (target pH 6.5–7.5). |
| 6 |
Visual Inspection |
Conduct line-of-sight inspection under adequate lighting (≥ 500 lux). Any visible soil triggers re-cleaning. |
| 7 |
Sanitisation |
Apply approved sanitiser per manufacturer instructions. Allow required contact time before rinse (if applicable). |
| 8 |
Final Verification |
Swab for ATP (Section 6) or allergen ELISAs (Section 8) as scheduled. Document release on pre-op checklist. |
1.3 Line Release Criteria
- No visible soil on any product contact surface.
- ATP readings < 30 RLU for equipment, < 10 RLU for product contact surfaces.
- Allergen ELISA (if required): negative result (< limit of detection).
- Pre-op checklist fully signed by sanitation lead and QA.
2. Operational Sanitation
2.1 Spill Management
| Spill Type |
Response |
Documentation |
| Dry product spill |
Stop production in area, sweep/vacuum immediately, inspect for cross-contact |
Spill Log FS-SSOP-F02 |
| Wet product/liquid spill |
Stop production, contain with absorbent pads, clean & sanitise the zone |
Spill Log FS-SSOP-F02 |
| Allergen spill |
Stop production, zone affected area, perform allergen cleaning per Section 8, ELISA swab before restart |
Allergen Incident Log FS-ALC-F03 |
| Chemical spill |
Evacuate area, follow SDS emergency procedures, notify EHS |
Chemical Spill Report FS-EHS-F01 |
2.2 Scheduled Break Cleaning
| Break |
Duration |
Activities |
| Mid-morning (15 min) |
Line speed reduction, scrape surfaces, remove debris, spot clean |
Dry sweep, empty waste bins, sanitise handwash stations |
| Lunch (30 min) |
Partial shutdown: dry clean, wet clean if allergen changeover, floor scrub |
As per zone schedule |
| End-of-shift |
Complete wet clean per Master Sanitation Schedule |
Full pre-op equivalent |
2.3 Allergen Changeover Cleaning
Refer to Section 8 (Allergen Clean Validation) and Allergen Control Program (FS-ALC-001). Between production of products containing different allergens, complete a full wet clean with intermediate rinse verification.
3. Master Sanitation Schedule (MSS)
3.1 Schedule Overview
The MSS covers all areas, equipment, and utilities. Tasks are assigned by frequency: daily, weekly, monthly, quarterly, semi-annual, annual.
3.2 Master Sanitation Schedule Matrix
| Area / Equipment |
Task |
Frequency |
Chemical |
Concentration |
Method |
Verification |
Responsible |
| Receiving Bay |
Floor scrub & drain clean |
Daily |
Alkaline Foam Cleaner |
2–3% v/v |
Apply foam, dwell 10 min, pressure rinse |
Visual + ATP weekly |
Sanitation Tech |
| Whole Seed Silo (S-101) |
Dry clean interior |
Weekly |
N/A (dry clean only) |
— |
Vacuum + manual wipe with food-grade cloth |
Visual + ATP monthly |
Production Lead |
| Flax Mill (M-201) |
Full wet clean |
Weekly (or allergen change) |
Chlorinated Alkaline |
3% v/v, 45 °C |
CIP cycle per SOP-CIP-01 |
ATP + ELISA post-clean |
Sanitation Lead |
| Oil Press Line (P-301) |
CIP (alkali-acid-sanitise) |
Weekly |
See Section 5 — CIP Procedure |
Per CIP cycle |
Automated CIP |
ATP + pH final rinse QA |
QA Specialist |
| Screw Conveyor (C-401) |
Disassemble & wet clean |
Monthly |
Neutral Detergent |
1.5% v/v, warm water |
Manual scrub with brush, rinse, sanitise |
Visual + ATP |
Sanitation Tech |
| Packaging Hopper (H-501) |
Full wet clean |
Weekly |
Acid Cleaner |
2% v/v, 40 °C |
Circulation 15 min, rinse, visual check |
ATP < 10 RLU |
QA |
| Magnetic Separator |
Clean magnet surfaces |
Daily |
Dry brush |
— |
Remove debris from magnet rods |
Visual |
Production |
| Sifting Screens |
Inspect & clean |
Every batch change |
Dry brush or compressed air (HEPA) |
— |
Brush screen mesh, check for tears |
Visual + mesh gauge |
QA |
| Floor Drains (all) |
Scrub & sanitise |
Daily |
Quaternary Ammonium |
200 ppm |
Foam, brush, rinse, sanitise |
ATP monthly |
Sanitation Tech |
| HVAC Vents |
Wipe & filter check |
Monthly |
Neutral Detergent |
1% v/v |
Wipe louvres, replace HEPA if needed |
Visual |
Maintenance |
| Cold Storage Room |
Floor & wall wash |
Monthly |
Alkaline Foam |
3% v/v |
Foam, dwell, pressure rinse |
Visual + ATP |
Sanitation Tech |
| Overhead Structures (pipes/trusses) |
Dust & debris removal |
Quarterly |
Dry vacuum + damp wipe |
— |
Vacuum, then damp cloth |
Visual |
Sanitation Lead |
| Lighting Fixtures |
Clean & inspect |
Quarterly |
Glass/plastic-safe cleaner |
Per label |
Wipe, inspect for cracks/missing sleeves |
Visual |
Maintenance |
| Waste Compactor Area |
Pressure wash |
Weekly |
Degreaser |
5% v/v |
Pressure wash, sanitise perimeter |
Visual |
Sanitation Tech |
3.3 Seasonal / Deep Clean Tasks
| Task |
Frequency |
Month(s) |
| Full mill disassembly & deep clean |
Annual |
Plant shutdown (August) |
| CIP chemical tank descaling |
Semi-annual |
March, September |
| Drain line jetting & camera inspection |
Annual |
January |
| Exterior wall & roof vent cleaning |
Annual |
May |
4. Cleaning Chemical Specifications
4.1 Approved Chemical Inventory
| Chemical Name |
Active Ingredient(s) |
Recommended Concentration |
Min Contact Time |
Temperature Range |
Approved Surfaces |
Rinse Required? |
| Alka-Clean Supreme |
Sodium hydroxide (10–15%), potassium hydroxide (5–10%) |
2–5% v/v |
10 min |
40–60 °C |
Stainless steel, plastic, rubber (EPDM) |
Yes — potable water |
| Chlor-Alkali Foam |
Sodium hypochlorite (3–5%), sodium hydroxide (5–10%) |
2–4% v/v |
10 min |
20–50 °C |
Stainless steel, tiled walls, floors |
Yes — potable water |
| Acid-Brite 50 |
Phosphoric acid (20–30%), nitric acid (5–10%) |
1–3% v/v |
5 min |
40–65 °C |
Stainless steel (passivates), glass |
Yes — potable water |
| Neutral Kleen |
Alkyl polyglycosides, non-ionic surfactants |
0.5–2% v/v |
5 min |
20–50 °C |
All food contact surfaces, soft metals |
Yes — potable water |
| Quat-San Plus |
Didecyl dimethyl ammonium chloride (10%) |
150–200 ppm |
30 sec to 1 min |
Cold–50 °C |
Stainless steel, plastic, floors, walls |
No (no-rinse sanitizer) |
| Peroxy-San 15 |
Peracetic acid (15%), hydrogen peroxide (10–15%) |
150–250 ppm |
30 sec to 2 min |
10–40 °C |
Stainless steel, glass, plastic (verify compatibility) |
No (no-rinse sanitizer) |
| Iodophor San |
Iodine complex (2%), phosphoric acid (10%) |
25–50 ppm iodine |
2 min |
20–40 °C |
Stainless steel, plastic |
No (no-rinse) |
4.2 Chemical Handling Requirements
- All chemicals stored in original containers or clearly labelled secondary containers.
- MSDS/SDS available in the chemical storage room and sanitation office.
- Personal protective equipment (PPE): chemical-resistant gloves, safety goggles, rubber boots, apron.
- Chemical dispensing stations calibrated quarterly.
- Follow all manufacturer concentration test strip verifications.
5. CIP Procedure — Oil Press Line
5.1 Equipment Covered
Oil press line including: press screw (P-301), filter housing (F-101), oil holding tank (T-201), centrifuge (C-101), transfer piping (DN50–DN100).
5.2 Standard CIP Cycle
| Phase |
Step |
Solution |
Concentration |
Temperature |
Time |
Return Criteria |
| 1 |
Pre-Rinse |
Potable water |
— |
50 °C |
5 min |
Effluent clear |
| 2 |
Alkali Wash |
Alka-Clean Supreme |
3% v/v |
60 °C |
15 min |
Circulation flow ≥ 1.5 m/s |
| 3 |
Intermediate Rinse |
Potable water |
— |
50 °C |
5 min |
pH 6.5–8.0; effluent clear |
| 4 |
Acid Wash |
Acid-Brite 50 |
2% v/v |
55 °C |
10 min |
— |
| 5 |
Final Rinse |
Potable water |
— |
Ambient |
5 min |
pH 6.5–7.5; conductivity < 50 µS/cm |
| 6 |
Sanitise |
Peroxy-San 15 |
200 ppm |
Ambient |
2 min |
Peracetic acid test strip ≥ 150 ppm |
| 7 |
Final Drain |
— |
— |
— |
2 min |
— |
5.3 Post-CIP Verification
- ATP swab of final rinse water in holding tank (target ≤ 10 RLU).
- Visual inspection of interior surfaces via access ports.
- Record all CIP parameters in CIP Log (FS-CIP-F01).
6. ATP Swabbing Verification
6.1 Protocol
ATP bioluminescence testing is conducted using a SystemSure Plus™ luminometer with Ultrasnap swabs.
6.2 ATP Limits
| Surface Category |
Target |
Warning |
Action / Corrective Action |
Product Contact (e.g., mill chamber, conveyor belt, hopper interior, packaging funnel) |
< 10 RLU |
10–30 RLU |
> 30 RLU: re-clean, re-test. > 300 RLU: quarantine area, notify QA Supervisor, root cause investigation. |
Non-Product Contact (Equipment) (e.g., equipment exteriors, control panels, framework) |
< 30 RLU |
30–100 RLU |
> 100 RLU: re-clean. > 300 RLU: investigation. |
Environment (e.g., floors, walls, drains, overheads) |
< 100 RLU |
100–300 RLU |
> 300 RLU: re-clean, root cause if recurrent. |
6.3 Corrective Action for ATP Exceedance (> 300 RLU)
- Stop line release.
- Isolate affected equipment.
- QA notifies Sanitation Lead and Production Supervisor.
- Re-clean per applicable MSS procedure.
- Re-swab within 30 minutes.
- If second failure: escalate to Food Safety Team for root cause investigation.
- Document on ATP Corrective Action Log (FS-SSOP-F03).
6.4 Sampling Frequency
- Product contact: Every pre-op release (daily) + post-allergen changeover.
- Non-product contact: Weekly rotating schedule.
- Environment: Monthly rotating schedule.
- Annual trend analysis reported to Food Safety Team.
7. Microbiological Environmental Monitoring
7.1 Zone Classification (Based on ISO 14644 / FDA Aseptic Guidance)
| Zone |
Definition |
Examples |
Target Organisms |
Sampling Method |
| Zone 1 |
Direct product contact surfaces |
Mill interior, oil press screw, hopper interior, conveyor belt |
Aerobic Plate Count (APC), Enterobacteriaceae, E. coli |
Contact plates, swabs |
| Zone 2 |
Non-product contact adjacent to Zone 1 |
Equipment frame, machine guards, control panel |
APC, Enterobacteriaceae, yeast & mould |
Contact plates, swabs |
| Zone 3 |
Indirect contact — floor, walls, drains near product |
Production floor, drains within 3 m of equipment |
APC, Listeria spp., yeast & mould |
Sponge swabs (drains), contact plates (walls) |
| Zone 4 |
Remote environment (outside production) |
Warehouse, hallways, break rooms |
APC, yeast & mould |
Settle plates, air samplers |
7.2 Sampling Plan
| Parameter |
Zone 1 |
Zone 2 |
Zone 3 |
Zone 4 |
| Number of sites |
10 |
8 |
6 |
4 |
| Frequency |
Weekly |
Weekly |
Monthly |
Monthly |
| APC target |
< 10 CFU/contact plate |
< 50 CFU/contact plate |
< 200 CFU/swab |
< 500 CFU/settle plate |
| APC action |
≥ 10 CFU: investigation |
≥ 100 CFU: investigation |
≥ 500 CFU: cleaning |
≥ 1000 CFU: cleaning |
| Enterobacteriaceae target |
< 1 CFU/plate |
< 5 CFU/plate |
— |
— |
| Listeria spp. |
— |
— |
Absent (in 25 g or swab) |
— |
| Yeast & mould target |
< 5 CFU/plate |
< 10 CFU/plate |
< 50 CFU/swab |
< 100 CFU/plate |
7.3 Corrective Actions for Pathogen Positives
- Any Zone 1 or Zone 2 Listeria or Salmonella positive: Immediate line stop, quarantine affected product, deep clean, root cause investigation, enhanced sampling (3× frequency for 4 weeks post-clearance).
- Zone 3 Listeria positive: Increase cleaning frequency, conduct vector analysis, swab adjacent Zone 2 sites.
8. Allergen Clean Validation — ELISA Swabbing
8.1 Purpose
Verify removal of allergen residues after changeover cleaning between products containing different allergens.
8.2 Target Allergens & ELISA Kits
| Allergen |
ELISA Kit (Supplier) |
Limit of Detection (LOD) |
Swab Area |
Acceptance Criteria |
| Gluten |
R-Biopharm Ridascreen® Gliadin |
5 ppm gliadin |
10 cm × 10 cm |
< LOD (negative) |
| Milk (β-lactoglobulin) |
R-Biopharm Ridascreen® β-Lactoglobulin |
2.5 ppm |
10 cm × 10 cm |
< LOD (negative) |
| Soy |
Neogen® Veratox® Soy |
2.5 ppm |
10 cm × 10 cm |
< LOD (negative) |
| Flaxseed |
In-house developed lateral flow (or 3rd party if available) |
LOD per kit insert |
10 cm × 10 cm |
< LOD (negative) |
| Mustard |
R-Biopharm Ridascreen® Mustard |
2 ppm |
10 cm × 10 cm |
< LOD (negative) |
8.3 Swabbing Protocol
- Select target allergen(s) based on previous product run.
- Identify worst-case swab sites (hard-to-clean areas: crevices, gaskets, dead ends, undersides of belts).
- Swab a 10 cm × 10 cm (100 cm²) area using the swab provided in the kit.
- Process swab per ELISA kit manufacturer instructions.
- Read result on plate reader at specified wavelength.
- Record in Allergen ELISA Log (FS-ALC-F02).
8.4 Corrective Action on Positive Result
- Do not release line for production.
- Re-clean entire line per wet clean procedure.
- Identify likely cause (incomplete disassembly, dead-leg, gasket residue).
- Re-swab.
- Only release after negative result.
9. Glass & Hard Plastic Register
9.1 Scope
Inventory of all brittle materials (glass, rigid plastic, ceramic, hard acrylic) in production, packaging, and storage areas.
9.2 Glass & Hard Plastic Register (Example)
| Item ID |
Type |
Location |
Qty |
Condition |
Inspection Frequency |
Last Inspected |
Inspected By |
| GL-001 |
Light fixture tube (LED shatter-proof) |
Receiving bay |
4 |
Intact |
Monthly |
2026-06-01 |
M. Chen |
| GL-002 |
Observation window (tempered) |
Mill S-101, 450 mm |
1 |
Intact |
Weekly |
2026-06-05 |
J. Smith |
| GL-003 |
Pressure gauge lens |
Oil press P-301 |
3 |
Intact |
Daily |
2026-06-07 |
L. Wang |
| GL-004 |
Clock face |
Production floor |
1 |
Intact |
Monthly |
2026-06-01 |
M. Chen |
| PL-001 |
Sanitation bucket (polycarbonate) |
Wet clean station |
6 |
1 cracked (removed) |
Weekly |
2026-06-05 |
J. Smith |
| PL-002 |
Scraper blade (UHMWPE) |
Conveyor C-401 |
2 |
Intact |
Weekly |
2026-06-05 |
J. Smith |
| PL-003 |
Cutting board (HDPE) |
Sample prep bench |
2 |
Intact |
Weekly |
2026-06-05 |
J. Smith |
| CR-001 |
Ceramic floor tile (round access) |
Drain D-103 |
1 |
Intact |
Monthly |
2026-06-01 |
M. Chen |
9.3 Glass Breakage Procedure
- Stop all production in affected area immediately.
- Evacuate personnel from zone (+ 5 m radius).
- Block entry with barriers and signage.
- DO NOT sweep — use adhesive tape or damp cloth to pick up fragments.
- Inspect all product, ingredients, and packaging within zone — quarantine any potentially contaminated materials.
- Document in Glass Breakage Incident Log (FS-SSOP-F04).
- Conduct root cause analysis within 24 hours.
- Replace with shatter-proof alternative (polycarbonate, acrylic, or shatter-film) wherever feasible.
9.4 Register Review
- Full inventory count: Monthly.
- Update on any addition/removal of brittle materials within 24 hours.
- Annual verification by Food Safety Team.
- All lighting in production must be LED shatter-proof type with protective sleeves.
10. Sanitation Records & Review
10.1 Records Maintained
| Record |
Retention |
Location |
| Pre-Operational Sanitation Checklist (FS-SSOP-F01) |
2 years |
QA Office |
| Operational Sanitation Log (FS-SSOP-F02) |
2 years |
Production Office |
| ATP Swabbing Log (FS-SSOP-F03) |
2 years |
QA Office |
| Glass Breakage Incident Log (FS-SSOP-F04) |
5 years |
Food Safety Office |
| Master Sanitation Schedule (MSS) |
Current + 2 years |
QA Office |
| CIP Cycle Log (FS-CIP-F01) |
2 years |
Maintenance Office |
| Allergen ELISA Log (FS-ALC-F02) |
2 years |
QA Office |
| Chemical Usage & Concentration Verification Log |
2 years |
Sanitation Office |
| Microbiological Environmental Monitoring Report |
3 years |
QA Office |
| Training Records — Sanitation Personnel |
Duration of employment + 1 year |
HR / QA |
10.2 Review Process
- Daily: Sanitation Lead reviews pre-op checklists and ATP results before line release.
- Weekly: QA Manager reviews operational logs and trend data.
- Monthly: Food Safety Team reviews all sanitation KPIs (ATP pass rate, microbiological trends, chemical usage).
- Annual: Full SSOP review and update by Food Safety Team Leader, incorporating regulatory changes, audit findings, and incident learnings.
10.3 Continuous Improvement
- Audit non-conformances related to sanitation trigger formal CAPA.
- Annual SSOP training for all sanitation, production, and QA personnel.
- Mock sanitation inspection performed once per quarter by internal audit team.
Appendices
- Appendix A: Sanitation Zone Map (floor plan with colour-coded zones)
- Appendix B: Chemical Dilution Chart (concentration × flow rate × time)
- Appendix C: ATP Swab Site Map (numbered locations)
- Appendix D: Environmental Monitoring Swab Site Map
End of Document — FS-SSOP-001